CIVIL ENGINEERING


Almbrücke Oberösterreich Scandic Crown Hotel Vienna Weitmannbrücke Niederösterreich
Schlinkerleitenstraße Oberösterreich Schwaigerbachbrücken Oberösterreich Badhausbrücke Niederösterreich
Gerstbachbrücke Niederösterreich S7 - airport-railway Perschlingbachbrücke
in Perschenegg
Structural Alteration railway station Absdorf/Hippersdorf A 8 - Innkreis motorway
cut-and-cover tunnel
A 9 - Phyrn motorway
cut-and-cover tunnel
ÖBB railway track section Aspang-Friedberg
Rehabilitation of 3 viaducts
Prefabricated High-Performance-Concrete unit bridge structures Kreisbachbrücke near Kreisbach


Click here to look at some pictures.

Almbrücke in Oberösterreich
First prestressed concrete structure of the world with compressive stressing reinforcement


Client: Amt der Oberösterreichischen Landesregierung
Activity: structural engineering, construction supervision *
Value of construction: EUR 1.06 Mio. (ATS 14.63 Mio.)
Time of construction: 1977
Description:
Erection of a road bridge (bridge class I), first prestressed concrete structure of the world with compressive stressing reinforcement (research project)
length
width
heigth
76.00 m
10.60 m
  2.50 m

* participation Civil Engineering Bureau Prof. Reiffenstuhl


TOP


Click here to look at some pictures.

Scandic Crown Hotel Vienna
A-1020 Vienna, Handelskai 269


Client: SKANSKA AB
Nordenskiöldsgatan 4
SW-211 02 Malmö

represented by:
PRADO
Grundstücksges.m.b.H.
Alsterufer 34
D-20354 Hamburg
Activity: structural engineering
tendering
evaluation of tenders
construction supervision
Value of construction: EUR 2.54 Mio. (ATS 35 Mio.)
Time of construction: 1986 to 1988
Description:
Erection of a bridge under full maintenance of the traffic of the Donauufer-railway and of the B12, Handelskai
deep foundation with bearing structures of prefabricated units and cast-in-place decks with transverse prestressing


TOP


Click here to look at some pictures.

Weitmannbrücke over Ybbs
in Waidhofen an der Ybbs


Client: Magistrat der Stadt Waidhofen an der Ybbs
Activity: structural engineering
Value of construction: EUR 1.09 Mio. (ATS 15.0 Mio.)
Time of construction: 1990
Description:
2-webs-T-beam bridge
spans: 20.00 m + 28.00 m + 20.00 m


TOP


Click here to look at some pictures.

HL-AG Lambach bypass
Underpass Schlinkerleitenstraße


Client: Eisenbahn-Hochleistungsstrecken AG
Vivenotgasse 8-12
A-1120 Vienna
Activity: structural engineering
tendering
evaluation of tenders
Value of construction: EUR 2.58 Mio. (ATS 35.5 Mio.)
Time of construction: 1991 to 1993
Description:
Underpass of a roadway as "white tube"
with new construction of five bearing structures under full maintenance of the railway working (west-railway)


TOP


Click here to look at some pictures.

HL-AG Lambach bypass
structural alteration Schwaigerbachbrücken


Client: Eisenbahn-Hochleistungsstrecken AG
Vivenotgasse 8-12
A-1120 Vienna
Activity: structural engineering
tendering
evaluation of tenders
Value of construction: EUR 1.90 Mio. (ATS 26.2 Mio.)
Time of construction: 1993 to 1994
Description:
New construction of two bearing structures under full maintenance of the railway working (west-railway)
structural alteration/reinforcement/heave/turning of an existing bearing structure


TOP



Click here to look at some pictures.

   

Badhausbrücke, Niederösterreich
first directly-trafficable High-Performance-Concrete bridge structure in Austria


Client: Municipality Tulln
Nußallee 4
A-3430 Tulln
Activity: structural engineering
tendering
evaluation of tenders
Value of construction: EUR 0.15 Mio. (ATS 2.1 Mio.)
Time of construction: 1997
Description:
Renewal of a steel and wood bridge by use of abutments and foundation piers


TOP



Click here to look at some pictures.

 

Gerstbachbrücke near Hainfeld, Niederösterreich


Client: Amt der Niederösterreichischen Landesregierung
Abteilung Güterwege
Landhausplatz 1, Haus 12
A-3109 St. Pölten
Activity: structural engineering
Time of construction: 1999
Description:
Renewal of a ferroconcrete bridge (system Visentini, built 1900), directly-trafficable High-Performance-Concrete surface


TOP



Click here to look at some pictures.

 

ÖBB Extension S7 - airport railway
Underpass Dreherstraße, Schwechat


Client: Österreichische Bundesbahnen
Elisabethstraße 18
A-1010 Vienna
Activity: structural engineering
tendering
Value of construction: EUR 2.91 Mio. (ATS 40.0 Mio.)
Time of construction: 1999 to 2000
Description:
Erection of an underpass (Dreherstraße) 560 m in length in form of an retaining wall and a bored pile wall (tied and not tied) and of a railway bridge (l=15.50 m) under full maintenance of railway working of the S7


TOP


Click here to look at some pictures.

Perschlingbachbrücke in Perschenegg


Client: MABA
Industriestraße 28
A-2601 Sollenau
Activity: structural engineering
Value of construction: EUR 0.07 Mio. (ATS 1.0 Mio.)
Time of construction: 2001
Description:
Prefabricated unit bridge with concrete topping of High-Performance-Concrete with directly-trafficable High-Performance-Concrete surface


TOP


Click here to look at some pictures.

ÖBB
Vienna Franz Josephs-railway station - Krems/Donau
Structural Alteration railway station Absdorf/Hippersdorf
Erection of an underground passageway


Client: Österreichische Bundesbahnen
Infrastruktur-Planung & Engineering
Technik
Elisabethstraße 18-20
A-1010 Vienna
Activity: submission planning
structural engineering
planning for tendering
Value of construction: EUR 900,000.00 (ATS 12.38 Mio.)
Time of construciton: February 2002 to December 2002
Description:
Erection of an underground passageway (width=5.20m/ span=5.60m) with staircases to the railway station building, the station platforms and to the planned Park&Ride parking place.


TOP


Click here to look at some pictures.

A 8 - Innkreis motorway
cut-and-cover tunnel


Winner of the Ingenieurpreis 2002 - A8 Baulos 5, OÖ



Client: ÖSAG
Rotenturmstraße 5-9
A-1010 Vienna

and

STRABAG AG
Dir. 16, Ingenieurtiefbau
Salzburger Straße 323
A-4021 Linz
Activity: structural engineering
Value of construction: EUR 28.27 Mio. (ATS 389 Mio.)
Time of construction: 2001 to 2003
Description:
Erection of a cut-and-cover tunnel 2,400 m in length as well as a gallery 380 m in length, built as a "white tube" with stages 24 m in length which were concreted in one go (approximately 950 m³)


TOP


Click here to look at some pictures.

A 9 - Phyrn motorway
cut-and-cover tunnel Ottsdorf


award winner of the ÖAMTC-tunnel-test 2005



Client: Strabag AG
Dir. 16, Ingenieurtiefbau
Salzburger Straße 323
A-4021 Linz
Activity: structural engineering
Value of construction: EUR 30.5 Mio. (ATS 419.7 Mio.)
Time of construction: November 2002 to May 2004
Description:
Erection of a cut-and-cover tunnel 1,940 m in length, built as a "white tube"


TOP


Click here to look at this picture.

ÖBB railway track section Aspang-Friedberg
Grollergraben-Viaduct
Wiesmath-Viaduct
Habischleiten-Viaduct


Client: Österreichische Bundesbahnen
Fahrweg
Ingenieurwesen/Dienstleistung
Nordbahnstraße 50
A-1020 Vienna
Activity: structural engineering
Time of construction: 2003
Description:
Rehabilitation of three viaducts built in the turn of the century. Installation of a carriageway trough and dewatering lines


TOP



Click here to look at this picture.

Prefabricated High-Performance-Concrete unit bridge structures
with directly-trafficable High-Performance-Concrete surface


Client: Amt der NÖ Landesregierung
Gruppe Straße, Abteilung Landesstraßen
Landhausplatz 1
A-3109 St. Pölten
Activity: structural engineering
planning of types
Planning: 2001 to 2002
Time of construction: as of 2003
Description:
Elaboration of a type paper for prefabricated unit bridge structures (bridge classI/road width=6.00 m and pavement width=1.25 m) with prefabricated High-Performance-Concrete units and with directly-trafficable High-Performance-Concrete surface (prefabricated units: span=5.00-11.00 m)


TOP



Click here to look at some pictures.

Kreisbachbrücke near Kreisbach,
L 5117.05


Client: Amt der NÖ Landesregierung
NÖ Straßendienst, NÖ Straßenbauabt. 5
Linzer Straße 106
A-3100 St. Pölten
Activity: submission planning
planning for tendering
structural engineering
Value of construction: EUR 0.15 Mio. (ATS 2.06 Mio.)
Time of construction: 2003
Description:
This object is a reference for the type paper "Prefabricated High-Performance-Concrete unit bridge structures with directly-trafficable High-Performance-Concrete surface".
The bearing structure is a simple bridge of three prefabricated High-Performance-Concrete units (each with a width of 2.60 m and with a span of 9.50 m) with directly-trafficable High-Performance-Concrete surface.
At the final condition the three prefabricated units are combined because of the surface and they are seen as gross cross section.


TOP


 